1 After completion of the procedure for the granting of a general licence, an amendment is required:
2 After the respective issuing procedure has been completed, an amendment to a licence or order is required in the event of any significant deviations from the original construction licence, operating licence, and licence for carrying out geological investigations, and orders regarding decommissioning and closure.
3 In the event of amendments that do not deviate significantly from the respective licence or order as cited in paragraph 2, but which may have an influence on nuclear safety or security, the holder is required to obtain a permit from the supervisory authorities.
4 All other amendments must be reported to the supervisory authorities.
5 In case of doubt:
1 Une modification de l’autorisation générale selon la procédure d’octroi est nécessaire:
2 Tout écart important par rapport à l’autorisation de construire ou à l’autorisation d’exploiter, à l’autorisation de procéder à des études géologiques ou à la décision relative à la désaffectation ou à la fermeture rend nécessaire la modification de l’autorisation ou de la décision, laquelle se fera selon la procédure respective de leur attribution.
3 Si les modifications ne s’écartent pas de manière importante d’une autorisation ou d’une décision au sens de l’al. 2, mais qu’elles peuvent influer sur la sécurité ou sur la sûreté nucléaire, l’exploitant doit demander un permis d’exécution aux autorités de surveillance.
4 Toute autre modification doit être annoncée aux autorités de surveillance.
5 En cas de doute, il appartient: