732.1 Nuclear Energy Act of 21 March 2003 (NEA)

732.1 Loi du 21 mars 2003 sur l'énergie nucléaire (LENu)

Art. 53 Consultation, publication and public inspection

1 After receiving an application, the Federal Office shall forward it to the cantonal authorities concerned and request them to submit an advisory opinion within three months. The Federal Office may extend the deadline in certain justified circumstances.

2 The application shall be published in the official gazette of each canton and commune concerned, as well as in the Swiss Federal Gazette, and made available for public inspection for a period of 30 days.

3 ...18

18 Repealed by Annex No 11 of the FA of 19 June 2020, with effect from 1 Jan. 2021 (AS 2020 4085; BBl 2018 4713).

Art. 53 Consultation, publication et mise à l’enquête

1 L’office transmet la demande d’autorisation aux cantons concernés et les invite à se prononcer dans les trois mois. Si la situation le justifie, il peut prolonger ce délai.

2 La demande d’autorisation doit être publiée dans les organes officiels des cantons et des communes concernés ainsi que dans la Feuille fédérale, et mise à l’enquête pendant 30 jours.

3 ...19

19 Abrogé par l’annexe ch. 11 de la LF du 19 juin 2020, avec effet au 1er janv. 2021 (RO 2020 4085; FF 2018 4817).

 