1 Any person who operates or decommissions a nuclear installation is obliged to safely manage all radioactive waste arising from that installation at their own cost. The obligation to manage and dispose of radioactive waste shall encompass the necessary preliminary activities such as research and geological investigations, as well as the timely provision of a deep geological repository.
2 The obligation to manage and dispose of radioactive waste is met if:
3 If a general licence for a nuclear power plant has been transferred to another licence holder (Article 66 paragraph 2), the previous and the new licence holder shall be responsible for the management of all radioactive waste and spent fuel produced up to the time of transfer of the licence.
4 The company responsible for the management of radioactive waste may only be liquidated with the prior consent of the Department.
1 Quiconque exploite ou désaffecte une installation nucléaire est tenu d’évacuer à ses frais et de manière sûre les déchets radioactifs produits par elle. Les travaux préparatoires indispensables, tels que la recherche et les études géologiques, ainsi que la préparation en temps utile d’un dépôt en profondeur font partie intégrante de l’obligation.
2 L’obligation d’évacuation est remplie lorsque:
3 En cas de transfert de l’autorisation générale pour une centrale nucléaire à un nouvel exploitant (art. 66, al. 2), l’ancien et le nouvel exploitants répondent de l’évacuation des déchets d’exploitation et des éléments combustibles usés produits jusqu’au transfert.
4 La dissolution de la société responsable de l’évacuation est soumise à l’approbation du département.