172.056.1 Federal Act of 21 June 2019 on Public Procurement (PPA)

172.056.1 Loi fédérale du 21 juin 2019 sur les marchés publics (LMP)

Art. 43 Abandonment

1 The contracting authority may abandon the award procedure, particularly if:

a.
it decides not to award the public contract for valid reasons;
b.
no tender meets the technical specifications or the other requirements;
c.
more advantageous tenders are to be expected due to changes in the framework conditions;
d.
the tenders submitted do not allow for economical procurement, or significantly exceed the cost framework;
e.
there are sufficient indications of an unlawful agreement affecting competition between the tenderers;
f.
a significant change in the goods, work or services requested becomes necessary.

2 Tenderers are not entitled to compensation in the event of a justified abandonment of the procedure.

Art. 43 Interruption

1 L’adjudicateur peut interrompre la procédure d’adjudication en particulier dans les cas suivants:

a.
il renonce, pour des motifs suffisants, à adjuger le marché public;
b.
aucune offre ne répond aux spécifications techniques ou aux autres exigences;
c.
en raison de modifications des conditions-cadres, des offres plus avantageuses sont attendues;
d.
les offres présentées ne permettent pas une acquisition économique ou dépassent nettement le budget;
e.
il existe des indices suffisants d’un accord illicite affectant la concurrence entre les soumissionnaires;
f.
une modification importante des prestations demandées est nécessaire.

2 En cas d’interruption justifiée de la procédure, les soumissionnaires n’ont pas droit à une indemnisation.

 

This document is not an official publication. Only the publication of the Federal Chancellery is legally binding.