220 Federal Act of 30 March 1911 on the Amendment of the Swiss Civil Code (Part Five: The Code of Obligations)

220 Loi fédérale du 30 mars 1911 complétant le code civil suisse (Livre cinquième: Droit des obligations)

Art. 378 IV. Impossibility of performance for reasons attributable to the customer

1 Where completion of the work is rendered impossible by chance occurrence affecting the customer, the contractor is entitled to payment for the work already done and of expenses incurred that were not included in the price.

2 Where the customer is at fault for the impossibility of performance, the contractor may also claim damages.

Art. 377 III. Résiliation par le maître moyennant indemnité

Tant que l’ouvrage n’est pas terminé, le maître peut toujours se départir du contrat, en payant le travail fait et en indemnisant complètement l’entrepreneur.

 