220 Federal Act of 30 March 1911 on the Amendment of the Swiss Civil Code (Part Five: The Code of Obligations)

220 Loi fédérale du 30 mars 1911 complétant le code civil suisse (Livre cinquième: Droit des obligations)

Art. 373 a. Firm commitment

1 Where the payment was fixed in advance as an exact amount, the contractor is obliged to produce the work for the agreed amount and may not charge more even if the work entailed more labour or greater expense than predicted.

2 However, where production of the work was prevented or seriously hindered by extraordinary circumstances that were unforeseeable or excluded according to the conditions assumed by both parties, the court may at its discretion authorise an increase in the price or the termination of the contract.

3 The customer must pay the full price even where the work has entailed less labour than predicted.

Art. 372 1. Exigibilité du prix

1 Le prix de l’ouvrage est payable au moment de la livraison.

2 Si des livraisons et des paiements partiels ont été convenus, le prix afférent à chaque partie de l’ouvrage est payable au moment de la livraison de cette partie.

 