220 Federal Act of 30 March 1911 on the Amendment of the Swiss Civil Code (Part Five: The Code of Obligations)

220 Loi fédérale du 30 mars 1911 complétant le code civil suisse (Livre cinquième: Droit des obligations)

Art. 365 2. Regarding materials

1 Where the contractor is responsible for supplying the materials, he is liable to the customer for their quality and has the same warranty obligation as a seller.

2 Where materials are supplied by the customer, the contractor must treat them with all due care, give account of how they are used and return any that remain unused to the customer.

3 If, when producing the work, the contractor notes defects in the materials supplied or in the designated construction site or if any other circumstance arises which might compromise the correct or timely production of the work, he must inform the customer immediately, failing which he shall himself be liable for any adverse consequences.

Art. 364 1. En général

1 La responsabilité de l’entrepreneur est soumise, d’une manière générale, aux mêmes règles que celle du travailleur dans les rapports de travail.246

2 L’entrepreneur est tenu d’exécuter l’ouvrage en personne ou de le faire exécuter sous sa direction personnelle, à moins que, d’après la nature de l’ouvrage, ses aptitudes ne soient sans importance.

3 Sauf usage ou convention contraire, l’entrepreneur est tenu de se procurer à ses frais les moyens, engins et outils qu’exige l’exécution de l’ouvrage.

246 Nouvelle teneur selon le ch. II art. 1 ch. 6 de la LF du 25 juin 1971, en vigueur depuis le 1er janv. 1972 (RO 1971 1461; FF 1967 II 249). Voir aussi les disp. fin. et trans. tit. X à la fin du texte.

 

This document is not an official publication. Only the publication of the Federal Chancellery is legally binding.
Ceci n’est pas une publication officielle. Seule la publication opérée par la Chancellerie fédérale fait foi. Ordonnance sur les publications officielles, OPubl.